Project Description

Due to permanent stress by lorries and forklifts, the ground sill at the warehouse had been wornout to an extent which even led to the bare reinforcement being visible.

The challenge has now been to rapidly and sustainably repair the damaged concrete layer in order to ensure least possible interruption of warehouse traffic. The product used was our fastsetting mortar MORTAR MIX. The damaged area was milled to create a load-bearing and coarse subbase, perfectly prepared for repair works. Then MORTAR MIX was applied with a layer thickness of 20 – 50 mm.

The job was completed after a total of 4 hours and warehouse operation could be reassumed.